The Regional Mobility Plan has set medium and long-term goals and strategies to extend the network and technological infrastructures of the Metropolitan Railway System.

The strengthening actions required in Torino and the first belt suburbs include the opening of the following stations: S. Paolo (n183), Borgata Quaglia-Gru (n186) and S. Luigi (n187), besides the creation of the new stops Dora (n184) and Zappata (n185). Moreover, the construction of Grosseto station (n188) is about to be completed.

DORA RAILWAY STATION
The project for the completion of the new Dora railway station, situated near piazza Baldissera between Porta Susa and Rebaudengo railway stations, envisages the construction of an underground station on three levels (pedestrian accesses, technical mezzanine and tracks). The project is financed by the National Recovery and Resilience Plan funds (measure 1.5).

general information

area name

Dora FS

address/district/city

Corso Principe Oddone, piazza Baldissera / Circoscrizione 4, Circoscrizione 7 / Torino

ownership

RFI

OPERATOR

RFI

intervention typology

New railway station

urban planning data

main intended use

Railway station

timing for area availability

start of works

2024

conclusion of works

2026